Requirements for Contracting Aluminum Skin Insulation Engineering

NegotiableUpdate on 05/06
Model
Nature of the Manufacturer
Producers
Product Category
Place of Origin

Overview

The contracting requirements for aluminum sheet insulation engineering are as follows: I will directly provide you with a list of contents that can be used for contract negotiation, bidding, quotation, and contract signing, covering qualifications, personnel, materials, processes, quality, safety, acceptance, and after-sales. All of them are the key points of on-site practical operation and can be directly used.

Product Details

Requirements for Contracting Aluminum Skin Insulation Engineering

1、 Qualification requirements for contracting (mandatory)

  1. possessProfessional contracting qualification for waterproof, anti-corrosion and insulation engineering (Level 2 or above).

  2. possessSafety Production LicenseThe personnel insurance is complete.

  3. Construction personnel must hold certificates:High altitude operation certificate, welder certificate, electrician certificateWaiting for the special operation certificate.

  4. can provideEnterprise business license, qualification certificate, safety permit, personnel identification documentsfor reference.

2、 Personnel and team requirements

  1. Fixed professional insulation team,No temporary assembly of odd jobs allowed.

  2. Each team must have:1 supervisor, 1 technician, 1 quality officer, and 1 safety officer.

  3. High altitude operations mustDouble rope safety belt, safety helmet, anti slip shoesIt is prohibited to work without a license.

3、 Material quality requirements (aluminum sheet+insulation layer+auxiliary materials)

1) Aluminum skin (outer protective layer)

  • Material:3003-H24 rust proof aluminum (industrial/chemical/outdoor)

  • ThicknessTank/equipment ≥ 0.8mm; pipeline ≥ 0.6mm; coastal/corrosive area ≥ 1.0mm

  • Surface: No scratches, no oxidation, no burrs,Fluorocarbon or polyester coating ≥ 25 μ m

  • Specification: Aluminum sheet coil/flat plate,Compliant with GB/T3880 standard

2) Insulation layer (rock wool/aluminum silicate/rubber/polyurethane)

  • Must be rated as Class A fire-resistant (rock wool/aluminum silicate) or Class B1 fire-resistant (rubber/polyurethane) according to national standards

  • stone woolDensity ≥ 100kg/m ³, thermal conductivity ≤ 0.04W/(m · K)

  • Polyurethane:Density ≥ 40kg/m ³, closed cell rate ≥ 95%, thermal conductivity ≤ 0.022

  • Materials entering the site must provide:Certificate of conformity, testing report, fire prevention report

3) Auxiliary materials

  • Rivet:Galvanized/aluminum alloy pop rivets, spacing 150-200mm

  • sealant:Neutral weather resistant silicone adhesive, -40 ℃~120 ℃

  • Aluminum foil tape:Thickened waterproof type, overlap ≥ 80mm

  • Strap/Tie Wire:Galvanized iron wire/stainless steel cable tie, spacing 300mm

4、 Construction process requirements (universal for tank/equipment)

1) Grassroots treatment

  • Tank surfaceRust removal, oil removal, and welding slag removalSmooth and clean.

  • The insulation nails are firmly welded, with an exposed length of ≥Aluminum skin thickness+5mm

2) Construction of insulation layer

  • Wrong seam pavingThe seams of the upper and lower layers should be staggered by ≥ 200mm, and no through seams should be allowed.

  • Layered compactionMulti layer insulation layer by layer with no hollowing or looseness.

  • Fill the gaps tightlyFor use around pipe openings, flanges, and manholesSame type insulation material+sealantFill in.

3) Moisture proof layer (necessary for cold insulation)

  • Full PackAluminum foil tape/waterproof clothOverlap ≥ 80mm, tightly sealed.

4) Aluminum skin outer protection construction (core)

  • Cutting:Mechanical cutting and bending, with an error of ≤ 2mm

  • Overlap:Longitudinal ≥ 50mm, circumferential ≥ 50mm; longitudinal seam facing downwards (downstream)

  • Fixed: rivet spacing150–200mmArrange neatly,Wooden hammer strikinganti-deformation

  • Node: Manhole, flange, valve fabricationDetachable aluminum protective cover, tightly sealed

  • Waterproof: all seams, nail holes, cornersFully apply weather resistant sealant

5、 Quality standard requirements

  1. Aluminum skin surfaceSmooth and flat, without pits, raised edges, or cracks

  2. Overall appearanceRound and beautiful, with straight seams and tight sealing

  3. insulation layerNo hollowing, detachment, or moisture

  4. After the completion of the project:No leakage, no condensation, no heat loss, no looseness

  5. Compliant with specifications:GB 50264-2013 Design Code for Thermal Insulation Engineering of Industrial Equipment and Pipelines

6、 Requirements for Safe and Civilized Construction

  1. sceneNeat enclosures, orderly stacking of materials, and daily cleaning of garbage

  2. High altitude operations must be set upQualified scaffolding/platformIt is strictly prohibited to throw materials

  3. Hot work requiresHot work permit+fire extinguisher+fire monitor

  4. During construction, the equipment, pipelines, and anti-corrosion coating of Party A shall not be damaged

Requirements for Contracting Aluminum Skin Insulation Engineering