Project ContentXinjiang Tianchi Energy General Gobi # 2 open-pit coal mine stacker reclaimer unmanned project
Implementation time: 2020
Project BackgroundThe first unmanned project in the coal industry
Project Overview:(1) After the successful operation of Unit # 2, the project will renew Units # 1 and # 3. Not only has it achieved the intelligence of the material yard, but it has also reduced labor costs, improved safety factors, and practiced the construction of smart mines.
(2) The feature is that it realizes the joint application of three unmanned systems on one system, achieving mutual switching and data redundancy among the three systems.
(3) Implement the interlock protection function between UWB personnel equipment and automatic control of the stacker reclaimer. When personnel or equipment enter the stacker reclaimer operation area, the system will automatically pop up an alarm, and the personnel tag will vibrate to prompt on-site workers to leave, preventing safety accidents from occurring.