Detailed operation method of salt spray test chamber:
1、 The prepared venue needs to be a separate laboratory. Connect the intake pipe, inlet pipe, and discharge pipe of the equipment, and prepare the air compressor. Install in a well ventilated area away from direct sunlight.
2、 The equipment needs to be operated, used, and maintained by a dedicated person
3、 Install the internal parts of the equipment: tower spray device, spray, funnel, round bar, V-shaped sample rack, etc. Then mix the purified water with industrial salt in a ratio of 1:19, pour it into a salt water bucket, and add water to the saturated bucket, box body, and sealed area
4、 After all the preparations are completed, close the box cover, check some problems on the pipes, confirm that it is OK, connect the power supply and power on, set the box temperature point, saturation barrel temperature point and test time you need to do on the instrument, or according to the test requirements, the equipment can be used for continuous and periodic spray. After all settings are OK, simply press' Run 'to proceed.
Some precautions to be taken during the use of the salt spray test chamber:
Pour the prepared sodium chloride brine into the brine replenishment tank, which automatically fills the brine into the preheating tank inside the test chamber, allowing the brine to flow into the brine preheating tank.
Open the switches of the automatic water inlet valve, drainage valve, and exhaust valve
Add water to the isolation sink to the pad position.
It is necessary to first check whether the equipment is deformed and whether the pipeline is unobstructed
The box materials used for neutral testing and CASS testing are different. The manufacturer's standard salt spray test chamber material is PVC board. If CASS test, copper accelerated acetic acid test or other tests are required, they must be explained before leaving the factory, otherwise improper operation may cause deformation of the box.